Red Dog Mtn. Contracting Ltd.
Information and History
Alternate names:- Red Dog Mtn. Contracting Ltd.
- Red Dog Mtn. Contracting Ltd. (Norman Wells) (BP-080092)
- Red Dog Mtn. Contracting Ltd. (Tulita) (BP-080070)
- PO Box 9, Tulita, NT (BP-080070) (physical)
- General Delivery, Norman Wells, NT (BP-080092) (physical)
- PO Box 9, Tulita (BP-080070) (mailing)
- General Delivery, Norman Wells (BP-080092) (mailing)
Search NWT Corporate Registry: Link
Published Contracts
Type | # of Contracts | Value of Contracts |
---|---|---|
Competitive Contracts (Published in Contracts Over $5k Reports) | 6 | $2,233,537.80 |
Contracts under Exisiting Standing Offer Agreement | 0 | - |
Sole Source Contracts | 25 | $1,412,444.17 |
Negotiated Contracts | 3 | $2,366,577.35 |
Fiscal Year | Dep't | Procurement | BIP Status | Process Type | Company Location | Original Amount | Change Orders | Final Amount |
---|---|---|---|---|---|---|---|---|
DOT | Steep Creek Grade Improvements | BIPed | Sole Source procurement | Tulita | $70,850.00 | 0 | $70,850.00 | |
DOT | Supply Lumber, Equipment and Labour | BIPed | Sole Source procurement | Tulita | $55,000.00 | 1 | $121,832.32 | |
DOT | Labour & Equipment Supply | BIPed | Sole Source procurement | Tulita | $65,375.51 | 0 | $65,375.51 | |
DOT | Haul Crusher Equipment | BIPed | Sole Source procurement | Tulita | $32,700.00 | 0 | $32,700.00 | |
DOT | Right of Way Clearing - Zone 4 | BIPed | Request for Tenders | Tulita | $101,300.00 | 0 | $101,300.00 | |
DOT | Equipment and Labour Supply | BIPed | Sole Source procurement | Tulita | $30,925.00 | 1 | $32,141.78 | |
DOT | Equipment and Labour Supply | BIPed | Sole Source procurement | Tulita | $52,141.34 | 0 | $52,141.34 | |
DOT | Equipment & Labour Supply | BIPed | Sole Source procurement | Tulita | $98,900.00 | 2 | $185,050.00 | |
DOT | Tulita MVWR Improvements | BIPed | Sole Source procurement | Tulita | $38,240.00 | 0 | $38,240.00 | |
DOT | Crusher Repair | BIPed | Sole Source procurement | Tulita | $9,151.70 | 0 | $9,151.70 | |
DOT | Repair and Maintenance of Tandem Truck | BIPed | Sole Source procurement | Tulita | $7,500.00 | 0 | $7,500.00 | |
DOT | Trench Construction | BIPed | Request for Tenders | Norman Wells | $15,500.00 | 1 | $25,265.00 | |
DOT | Equipment Rental and Labour Hours Tulita | BIPed | Sole Source procurement | Tulita | $69,130.00 | 1 | $77,100.37 | |
PWS | Haul Building Materials | BIPed | Sole Source procurement | Tulita | $13,340.00 | 0 | $13,340.00 | |
DOT | Equipment and labour - Little Smith Cree | BIPed | Sole Source procurement | Tulita | $48,700.00 | 1 | $51,675.00 | |
DOT | Winter Road Construction | BIPed | Sole Source procurement | Tulita | $27,800.00 | 0 | $27,800.00 | |
DOT | Drainage Improvements and Grade Repairs | BIPed | Sole Source procurement | Tulita | $55,400.00 | 0 | $55,400.00 | |
DOT | Equipment Rental | BIPed | Sole Source procurement | Tulita | $96,600.00 | 2 | $133,645.00 | |
DOT | Tulita Bypass Repairs-Equipment Rental | BIPed | Sole Source procurement | Tulita | $21,150.00 | 0 | $21,150.00 | |
DOT | Mechanical Repairs to Heavy Equipment | BIPed | Sole Source procurement | Norman Wells | $20,130.82 | 0 | $20,130.82 | |
DOT | Equipment Repair | BIPed | Sole Source procurement | Tulita | $19,947.90 | 0 | $19,947.90 | |
DOT | Tulita Bypass Road | BIPed | Sole Source procurement | Tulita | $154,070.00 | 0 | $154,070.00 | |
DOT | Stockpiling of Granular Materials | BIPed | Sole Source procurement | Tulita | $24,896.00 | 0 | $24,896.00 | |
DOT | Yellowknife Airport North Apron / Colvil | BIPed | Sole Source procurement | Tulita | $24,043.05 | 0 | $24,043.05 | |
DOT | EK-35 Application | BIPed | Sole Source procurement | Tulita | $33,250.00 | 2 | $99,253.38 | |
DOT | Equipment Rental for Tulita Airport Runw | BIPed | Sole Source procurement | Tulita | $8,090.00 | 0 | $8,090.00 | |
NWTHC | Ship, Supply & Stock pile | BIPed | Negotiated procurement | Tulita | $145,622.00 | 0 | $145,622.00 | |
NWTHC | Site Development | BIPed | Sole Source procurement | Tulita | $66,920.00 | 0 | $66,920.00 | |
DOT | Winter Road Construction and Maintenance - Zone 4 | BIPed | Request for Tenders | Tulita | - | 2 | $33,370.00 | |
DOT | MVWR - Km 794 -942 -Grade Improvemnet an | BIPed | Negotiated procurement | Tulita | $756,598.93 | 0 | $756,598.93 | |
DOT | Hauling and Stockpiling of Granular Mate | BIPed | Negotiated procurement | Tulita | $1,195,980.00 | 3 | $1,464,356.42 | |
DOT | WINTER ROAD CONSTRUCTION AND MAINTENANCE | BIPed | Request for Proposals | Tulita | $773,550.00 | 1 | $1,115,650.00 | |
DOT | WINTER ROAD CONSTRUCTION AND MAINTENANCE | BIPed | Request for Proposals | Tulita | - | 2 | $365,380.00 | |
DOT | WINTER ROAD CONSTRUCTION AND MAINTENANCE | BIPed | Request for Proposals | Tulita | - | 3 | $592,572.80 |
Bid Summary
Type | # of Bids | # of Successful Bids | Value of Successful Bids |
---|---|---|---|
Standing Offer Agreements (SOA) | 1 | 1 | - |
Requests for Proposals (RFP) | 1 | 1 | $773,550.00 |
Tenders (RFT) | 13 | 5 | $1,492,525.00 |
Request for Qualification (RFQ) | 0 | 0 | - |
Totals | 15 | 7 | $2,266,075.00 |