Bridgeworks - Blackwater River Bridge Project

Contract ID: CT100810
Status

This contract was awarded by Transportation to Stan Dean & Sons Ltd..

The status of this contract is unknown as start and end dates were not reported.

There were 2 change orders.

Dates
A rectangle of color grey representing the period of progress A circle of color green representing the start of progress A circle of color red representing the end of progress
Start Date
Unknown
Current End Date
Unknown
Potential End Date
Unknown

Tender Description

Bridgeworks - Blackwater River Bridge Pr

Details

Fiscal Year:
Buyer:
Transportation

Supplier:
Stan Dean & Sons Ltd.
Supplier BIP Status:
BIP Registered
Supplier Location:
Hay River

Original Value:
None
Change Orders:
$856,083.16 (2 changes)
Current Value:
$856,083.16

Community:
Wrigley (Dehcho)
Process:
Request for Tenders
Method:
Open (Competitive)
Procurement Type:
Construction
Category:
Road Construction Services

Contract Added:
Jan. 24, 2018
Source:
Contracting Report

Contract Change Orders

Fiscal Year Change Order Number Change Order Value
2010-11 1 (unknown)*
2010-11 2 $856,083.16

* The GNWT only publishes combined change order values so when there are multiple change orders in a fiscal year it is not possible to determine the reason or value for individual change orders.