ENR Fuel Transfer Deck
Contract ID: SC419611
Award dates for non-competitive contracts are not disclosed by the GNWT. Dates below are based on the publishing/tabling of the appropraite Contracting Report.
Status
This contract was awarded by Public Works & Services to Structure All Consulting Engineers Ltd..
The contract is complete.
There were 0 change orders.
Dates
- Start Date
- Jan 13, 2010
- Current End Date
- Mar 31, 2010
- Potential End Date
- Unknown
Description
Provide A/E consulting services for the design of a fuel transfer deck, incorporating the secondary bermed containment area referenced in the PPD specifications for the ENR compound located in Fort Smith, NT
Details
- Fiscal Year:
- Buyer:
- Public Works & Services
- Contract Dates:
- to
- Supplier:
- Structure All Consulting Engineers Ltd.
- Supplier BIP Status:
- BIP Registered
- Supplier Location:
- Yellowknife
- Original Value:
- $7,570.50
- Change Orders:
- --
- Current Value:
- $7,570.50
- Community:
- Fort Smith (South Slave)
- Process:
- SOA Release (Master SOA: SO417641)
- Method:
- Selective (Prequalified)
- Procurement Type:
- Services
- Category:
- Engineering Consulting
This is a Standing Offer Agreement (SOA) Release, which means it has been contracted under the terms of an existing Standing Offer agreement. The GNWT does not generally track or disclose which agreement these releases are related to.However, in this case, we know the master agreement is SO417641.
- Contract Added:
- Jan. 24, 2018
- Source:
- Contracting Report
Help us improve OpenNWT