ENR Fuel Transfer Deck

Contract ID: SC419611
Award dates for non-competitive contracts are not disclosed by the GNWT. Dates below are based on the publishing/tabling of the appropraite Contracting Report.
Status

This contract was awarded by Public Works & Services to Structure All Consulting Engineers Ltd..

The contract is complete.

There were 0 change orders.

Dates
A rectangle of color grey representing the period of progress A circle of color green representing the start of progress A circle of color red representing the end of progress
Start Date
Jan 13, 2010
Current End Date
Mar 31, 2010
Potential End Date
Unknown

Description

Provide A/E consulting services for the design of a fuel transfer deck, incorporating the secondary bermed containment area referenced in the PPD specifications for the ENR compound located in Fort Smith, NT

Details

Fiscal Year:
Buyer:
Public Works & Services

Contract Dates:
to

Supplier:
Structure All Consulting Engineers Ltd.
Supplier BIP Status:
BIP Registered
Supplier Location:
Yellowknife

Original Value:
$7,570.50
Change Orders:
--
Current Value:
$7,570.50

Community:
Fort Smith (South Slave)
Process:
SOA Release (Master SOA: SO417641)
Method:
Selective (Prequalified)
This is a Standing Offer Agreement (SOA) Release, which means it has been contracted under the terms of an existing Standing Offer agreement. The GNWT does not generally track or disclose which agreement these releases are related to.However, in this case, we know the master agreement is SO417641.
Procurement Type:
Services
Category:
Engineering Consulting

Contract Added:
Jan. 24, 2018
Source:
Contracting Report

Contract Disclosure Report Entries

Fiscal Year Report Period Start Report Period Ending Source
2009-10 April 1, 2009 March 31, 2010 Report
2009-10 Jan. 13, 2010 March 31, 2010 Report