Prohibition Creek Bridge Approach Works

Contract ID: SC795086
Award dates for non-competitive contracts are not disclosed by the GNWT. Dates below are based on the publishing/tabling of the appropraite Contracting Report.
Status

This contract was awarded by Transportation to HRN Contracting Ltd.

The status of this contract is unknown as start and end dates were not reported.

There were 0 change orders.

Dates
A rectangle of color grey representing the period of progress A circle of color green representing the start of progress A circle of color red representing the end of progress
Start Date
Unknown
Current End Date
Unknown
Potential End Date
Unknown

Tender Description

Prohibition Creek Bridge Approach Works

Details

Fiscal Year:
Buyer:
Transportation

Supplier:
HRN Contracting Ltd
Supplier BIP Status:
BIP Registered
Supplier Location:
Norman Wells

Original Value:
$52,320.00
Change Orders:
--
Current Value:
$52,320.00

Community:
Norman Wells (Sahtu)
Process:
Sole Source
Method:
Direct
Procurement Type:
Construction
Category:
Road Construction Services

Contract Added:
Jan. 24, 2018
Source:
Contracting Report