Upgrade Design of the Bunkhouse
Event/Procurement ID: CT100367
This procurement
closed
Description
Upgrade Design of the Bunkhouse
Details
- Published:
- Fiscal Year:
- Buyer:
- Public Works & Services
- BIP Locations:
- Fort Simpson (Dehcho)
- BIP Applies:
- Yes
- AIT Applies:
- Yes
- Security Required:
- Yes
- Process:
- Request for Tenders
- Method:
- Open (Competitive)
- Procurement Type:
- Construction
- Category:
- Building Construction General
- Closing:
- Status:
- Awarded
- Advertisement:
- View details
- Source Link:
- This tender was scraped from a GNWT Contract System that is no longer online.
- Last checked:
- n/a
Posted Bids (4 bids)
Bidder | Status | Bid Price | NWT Adjustment | NWT/Local Adjustment | Adjusted Bid Price | Contract Price |
---|---|---|---|---|---|---|
C.A.B. Construction Ltd. | $595,944.00 | $169,815.00 | $426,129.00 | $485,245.95 | -- | |
Energy Efficient Technologies Inc. | $349,887.22 | -- | -- | -- | -- | |
Hovat Construction (1985) Ltd. | $852,000.00 | $802,000.00 | $50,000.00 | $721,700.00 | -- | |
Rowe's Construction Ltd. | Successful | $431,150.99 | $321,212.99 | $109,938.00 | $360,981.44 | $431,150.99 |
Related Contracts
Fiscal Year | Contract # | Supplier | BIP Status | Supplier Location | Original Value | Change Orders | Change Value | Final Value |
---|---|---|---|---|---|---|---|---|
2006-07 | CT100367 | Rowe's Construction Ltd. | BIP Registered | Hay River | $431,150.99 | 7 | $95,859.63 | $527,010.62 |
Help us improve OpenNWT