N'Dullee Crossing Ice Removal

Contract ID: SC795313
Award dates for non-competitive contracts are not disclosed by the GNWT. Dates below are based on the publishing/tabling of the appropraite Contracting Report.
Status

This contract was awarded by Transportation to Pedzeh Ki Contractors Limited.

The contract is complete.

There were 0 change orders.

Dates
A rectangle of color grey representing the period of progress A circle of color green representing the start of progress A circle of color red representing the end of progress
Start Date
May 04, 2015
Current End Date
May 13, 2015
Potential End Date
Unknown

Description

Remove ice from north landing to commence ferry operations

Details

Fiscal Year:
Buyer:
Transportation
Reported Contract Buyer:

Contract Dates:
to

Supplier:
Pedzeh Ki Contractors Limited
Supplier BIP Status:
--
Supplier Location:
Wrigley, NT

Original Value:
$12,795.00
Change Orders:
--
Final Value:
$12,795.00

Community:
--
Process:
Sole Source
Method:
Direct
Procurement Type:
Construction
Category:
--

Contract Added:
Feb. 1, 2024
Source:
CRRS Extract

Contract Disclosure Report Entries

Fiscal Year Report Period Start Report Period Ending Source
2015-16 May 4, 2015 May 13, 2015 Report