Centennial Library Technical Upgrades

Contract ID: CT041524
Award dates for non-competitive contracts are not disclosed by the GNWT. Dates below are based on the publishing/tabling of the appropraite Contracting Report.
Status

This contract was awarded by Public Works & Services to A.D. WILLIAMS ENGINEERING INC..

The contract is complete.

There were 0 change orders.

Dates
A rectangle of color grey representing the period of progress A circle of color green representing the start of progress A circle of color red representing the end of progress
Start Date
Jul 27, 2004
Current End Date
Mar 31, 2005
Potential End Date
Unknown

Description

Heating system upgrade, install barrier free washroom, replace windows, other miscellaneous upgrades

Details

Fiscal Year:
Buyer:
Public Works & Services

Contract Dates:
to

Supplier:
A.D. WILLIAMS ENGINEERING INC.
Supplier BIP Status:
BIP Registered
Supplier Location:
Yellowknife

Original Value:
$24,000.00
Change Orders:
--
Current Value:
$24,000.00

Community:
Hay River (South Slave)
Process:
Sole Source
Method:
Direct
Procurement Type:
Services
Category:
Engineering Consulting

Contract Added:
Jan. 24, 2018
Source:
Contracting Report

Contract Disclosure Report Entries

Fiscal Year Report Period Start Report Period Ending Source
2004-05 April 1, 2004 March 31, 2005 Report
2004-05 July 27, 2004 March 31, 2005 Report