Ductwork Replacement
Contract ID: SC383708
Status
This contract was awarded by Public Works & Services to Dowland Contracting Ltd..
The contract is complete.
There were 0 change orders.
Dates
- Start Date
- Aug 31, 2004
- Current End Date
- Sep 30, 2004
- Potential End Date
- Unknown
Description
Contractor to supply all labour,material, equipemnt and tools necessary to install insulated exhaust ductwork from gymnasuim AHU to exterior that has been damaged or removed when fire occured in Samuel Hearne Secondary School in accordance with sketch. Contractor to supply all labour and material, as required to install Owner supplied exterior 108 w x 48 h louver for gymnasuim AHU.
Details
- Fiscal Year:
- Buyer:
- Public Works & Services
- Contract Dates:
- to
- Supplier:
- Dowland Contracting Ltd.
- Supplier BIP Status:
- BIP Registered
- Supplier Location:
- Yellowknife
- Original Value:
- $9,465.00
- Change Orders:
- --
- Current Value:
- $9,465.00
- Community:
- Inuvik (Beaufort-Delta)
- Process:
- Request for Tenders
- Method:
- Open (Competitive)
- Procurement Type:
- Services
- Category:
- Mechanical Contractor
- Contract Added:
- Jan. 24, 2018
- Source:
- Contracting Report
Help us improve OpenNWT