Supply Of Labour And Equipment, Highway No. 1, NWT, KM 20

Contract ID: SC790073
Award dates for non-competitive contracts are not disclosed by the GNWT. Dates below are based on the publishing/tabling of the appropraite Contracting Report.
Status

This contract was awarded by Transportation to Carter Industries Ltd.

The contract is complete.

There were 0 change orders.

Dates
A rectangle of color grey representing the period of progress A circle of color green representing the start of progress A circle of color red representing the end of progress
Start Date
Aug 02, 2004
Current End Date
Aug 31, 2004
Potential End Date
Unknown

Description

The work consists of the supply of labour and equipment, as directed by the on-site Engineer, for the completion of repairs to the culvert at KM 20 on Highway No. 1.

Details

Fiscal Year:
Buyer:
Transportation

Contract Dates:
to

Supplier:
Carter Industries Ltd
Supplier BIP Status:
NWT Non-BIP
Supplier Location:
Hay River

Original Value:
$30,675.00
Change Orders:
--
Current Value:
$30,675.00

Community:
Hay River (South Slave)
Process:
SOA Release (Master SOA: SO049710)
Method:
Selective (Prequalified)
This is a Standing Offer Agreement (SOA) Release, which means it has been contracted under the terms of an existing Standing Offer agreement. The GNWT does not generally track or disclose which agreement these releases are related to.However, in this case, we know the master agreement is SO049710.
Procurement Type:
Construction
Category:
Road Construction Services

Contract Added:
Jan. 24, 2018
Source:
Contracting Report

Contract Disclosure Report Entries

Fiscal Year Report Period Start Report Period Ending Source
2004-05 April 1, 2004 March 31, 2005 Report
2004-05 Aug. 2, 2004 Aug. 31, 2004 Report