Minor Partition Renovations - Ecole Allain St. Cyr

Contract ID: SC790570
Status

This contract was awarded by Public Works & Services to Doycon Northern Inc..

The contract is complete.

There were 0 change orders.

Dates
A rectangle of color grey representing the period of progress A circle of color green representing the start of progress A circle of color red representing the end of progress
Start Date
Aug 25, 2005
Current End Date
Aug 29, 2005
Potential End Date
Unknown

Description

Build a prefinished insulated wall up against one side of the operable partition. Frame and trim opening of new partition at location of the operable wall doors. Insulate above and at ends of walls. Owner will install operable partition.

Details

Fiscal Year:
Buyer:
Public Works & Services

Contract Dates:
to

Supplier:
Doycon Northern Inc.
Supplier BIP Status:
BIP Registered
Supplier Location:
Yellowknife

Original Value:
$6,500.00
Change Orders:
--
Current Value:
$6,500.00

Community:
Yellowknife (North Slave)
Process:
Request for Proposal
Method:
Open (Competitive)
Procurement Type:
Construction
Category:
Building Construction General

Contract Added:
Jan. 24, 2018
Source:
Contracting Report

Contract Disclosure Report Entries

Fiscal Year Report Period Start Report Period Ending Source
2005-06 April 1, 2005 March 31, 2006 Report
2005-06 Aug. 25, 2005 Aug. 29, 2005 Report