South Mackenzie Correctional Centre - Kitchen Renovation

Contract ID: CT100432
Status

This contract was awarded by Public Works & Services to B & T Plumbing and Heating.

The contract is complete.

There were 3 change orders.

Dates
A rectangle of color grey representing the period of progress A circle of color green representing the start of progress A circle of color red representing the end of progress
Start Date
Sep 29, 2006
Current End Date
May 12, 2007
Potential End Date
Unknown

Description

Change the range hood, 2 new exhaust fans on the roof, new fire suppression system, new floor for the kitchen and freezer

Details

Fiscal Year:
Buyer:
Public Works & Services

Contract Dates:
to

Supplier:
B & T Plumbing and Heating
Supplier BIP Status:
BIP Registered
Supplier Location:
Hay River

Original Value:
$113,900.00
Change Orders:
$25,536.98 (3 changes)
Current Value:
$139,436.98

Community:
Hay River (South Slave)
Process:
Request for Tenders
Method:
Open (Competitive)
Procurement Type:
Construction
Category:
Building Construction General

Contract Added:
Jan. 24, 2018
Source:
Contracting Report

Change Orders (Contract Amendments)

Fiscal Year Change Order Number Change Order Value
2006-07 1. cc40487 $21,136.98
2006-07 2. cc404979 $3,437.50
2006-07 3. cc405942 $962.50

* The GNWT only publishes combined change order values so when there are multiple change orders in a fiscal year it is not possible to determine the reason or value for individual change orders.

Contract Disclosure Report Entries

Fiscal Year Report Period Start Report Period Ending Source
2006-07 April 1, 2006 March 31, 2007 Report
2006-07 Sept. 29, 2006 Dec. 29, 2006 Report