Giant Mine Wind Project

Contract ID: SC403868
Award dates for non-competitive contracts are not disclosed by the GNWT. Dates below are based on the publishing/tabling of the appropraite Contracting Report.
Status

This contract was awarded by Industry, Tourism and Investment to Enviro Power Inc..

The contract is complete.

There were 0 change orders.

Dates
A rectangle of color grey representing the period of progress A circle of color green representing the start of progress A circle of color red representing the end of progress
Start Date
Nov 23, 2006
Current End Date
Feb 28, 2007
Potential End Date
Unknown

Description

Contractor is to analyze the Giant Mine site and consider various specific locations for wind monitoring and an eventual turbine installation.

Details

Fiscal Year:
Buyer:
Industry, Tourism and Investment

Contract Dates:
to

Supplier:
Enviro Power Inc.
Supplier BIP Status:
NWT Non-BIP
Supplier Location:
Yellowknife

Original Value:
$15,000.00
Change Orders:
--
Current Value:
$15,000.00

Community:
Yellowknife (North Slave)
Process:
Sole Source
Method:
Direct
Procurement Type:
Services
Category:
Technical Services

Contract Added:
Jan. 24, 2018
Source:
Contracting Report

Contract Disclosure Report Entries

Fiscal Year Report Period Start Report Period Ending Source
2006-07 April 1, 2006 March 31, 2007 Report
2006-07 Nov. 23, 2006 Feb. 28, 2007 Report