Frog Creek Overpass Repair
Contract ID: SC791049
Status
This contract was awarded by Transportation to 4831 NWT Ltd. o/a L.J.'s Contracting.
The contract is complete.
There was 1 change order.
Dates
- Start Date
- Aug 01, 2006
- Current End Date
- Aug 14, 2006
- Potential End Date
- Unknown
Description
Excavate, Load, Haul, Dump, Place and Compact 600 cubic metre Shale from Km 141 pit.
Details
- Fiscal Year:
- Buyer:
- Transportation
- Contract Dates:
- to
- Supplier:
- 4831 NWT Ltd. o/a L.J.'s Contracting
- Supplier BIP Status:
- BIP Registered
- Supplier Location:
- Fort McPherson
- Original Value:
- $15,000.00
- Change Orders:
- $35,590.00 (1 change)
- Current Value:
- $50,590.00
- Community:
- Fort McPherson (Beaufort-Delta)
- Process:
- Request for Tenders (Contract: Tender)
- Method:
- Open (Competitive)
- Procurement Type:
- Services
- Category:
- Highway Maintenance
- Contract Added:
- Jan. 24, 2018
- Source:
- Contracting Report
Change Orders (Contract Amendments)
Fiscal Year | Change Order Number | Change Order Value |
---|---|---|
2006-07 | 1. CC403126 | $35,590.00 |
* The GNWT only publishes combined change order values so when there are multiple change orders in a fiscal year it is not possible to determine the reason or value for individual change orders.