Asbestos work in SAMS

Contract ID: SC791258
Award dates for non-competitive contracts are not disclosed by the GNWT. Dates below are based on the publishing/tabling of the appropraite Contracting Report.
Status

This contract was awarded by Public Works & Services to 984339 NWT Ltd. o/a Arctic Bui.

The contract is complete.

There were 0 change orders.

Dates
A rectangle of color grey representing the period of progress A circle of color green representing the start of progress A circle of color red representing the end of progress
Start Date
Jan 11, 2007
Current End Date
Feb 28, 2007
Potential End Date
Unknown

Description

Contractor to supply labour and material to caulk every seam, crack and or hole in the ceiling and walls of SAMS upper wings. Contractor to spray foam any holes too big to caulk. Contractor to caulk gym stage and ceiling. Contractor to spray foam and seal around all splinkler pipes. Contractor to seal all door trim, lights and basboard.

Details

Fiscal Year:
Buyer:
Public Works & Services

Contract Dates:
to

Supplier:
984339 NWT Ltd. o/a Arctic Bui
Supplier BIP Status:
BIP Registered
Supplier Location:
Inuvik

Original Value:
$40,525.84
Change Orders:
--
Current Value:
$40,525.84

Community:
Inuvik (Beaufort-Delta)
Process:
Sole Source
Method:
Direct
Procurement Type:
Services
Category:
Building Maintenance

Contract Added:
Jan. 24, 2018
Source:
Contracting Report

Contract Disclosure Report Entries

Fiscal Year Report Period Start Report Period Ending Source
2006-07 April 1, 2006 March 31, 2007 Report
2006-07 Jan. 11, 2007 Feb. 28, 2007 Report