Relocate 18m Portable Bridge
Contract ID: SC791300
Status
This contract was awarded by Transportation to Hodgson's Contracting (2005) Inc..
The contract is complete.
There were 0 change orders.
Dates
- Start Date
- Mar 15, 2007
- Current End Date
- Mar 23, 2007
- Potential End Date
- Unknown
Description
The Contractor is to remove, upon road closure, an 18 m bridge and haul to a secure storage area of the Contractor's choice; store it until the Department of Transportation arranges for barging. The bridge is then to be transported to the barge location and loaded onto the barge for transportation south.
Details
- Fiscal Year:
- Buyer:
- Transportation
- Reported Contract Buyer:
- Contract Dates:
- to
- Supplier:
- Hodgson's Contracting (2005) Inc.
- Supplier BIP Status:
- --
- Supplier Location:
- Norman Wells, NT
- Original Value:
- $2,500.00
- Change Orders:
- --
- Final Value:
- $2,500.00
- Community:
- --
- Process:
- Request for Tenders
- Method:
- Open (Competitive)
- Procurement Type:
- Services
- Category:
- --
- Contract Added:
- Feb. 1, 2024
- Source:
- CRRS Extract
Contract Disclosure Report Entries
Fiscal Year | Report Period Start | Report Period Ending | Source |
---|---|---|---|
2006-07 | March 15, 2007 | March 23, 2007 | Report |