Foundation Remediation Grandfather Ayah School and Health Centre,

Contract ID: CT100553
Status

This contract was awarded by Public Works & Services to Weitzel's Construction Ltd..

The contract is complete.

There were 8 change orders.

Dates
A rectangle of color grey representing the period of progress A circle of color green representing the start of progress A circle of color red representing the end of progress
Start Date
Jun 14, 2007
Current End Date
Sep 30, 2008
Potential End Date
Unknown

Description

Labour Contract - materials supplied by the GNWT. Contractor to supply labour, equipment and tools to remediate the foundations of the Grandfather Ayah School and the Health Centre in Deline as per the drawings and specifications issued. Completion date is September, 2007.

Details

Fiscal Year:
Buyer:
Public Works & Services

Contract Dates:
to

Supplier:
Weitzel's Construction Ltd.
Supplier BIP Status:
BIP Registered
Supplier Location:
Inuvik

Original Value:
$889,000.00
Change Orders:
$143,310.50 (8 changes)
Current Value:
$1,032,310.50

Community:
Deline (Sahtu)
Process:
Request for Tenders
Method:
Open (Competitive)
Procurement Type:
Construction
Category:
Building Construction General

Contract Added:
Jan. 24, 2018
Source:
Contracting Report

Change Orders (Contract Amendments)

Fiscal Year Change Order Number Change Order Value
2007-08 1. CO99886 $29,705.00
2007-08 2. CO99902 -$41,976.50
2007-08 3. CO99903 $1,520.00
2007-08 4. CO99906 (unknown)*
2007-08 5. CO99943 $55,080.00
2007-08 6. CO99944 $25,200.00
2008-09 7. CO99983 $69,810.00
2008-09 8. CO99987 $3,972.00

* The GNWT only publishes combined change order values so when there are multiple change orders in a fiscal year it is not possible to determine the reason or value for individual change orders.

Contract Disclosure Report Entries

Fiscal Year Report Period Start Report Period Ending Source
2007-08 April 1, 2007 March 31, 2008 Report
2008-09 April 1, 2008 March 31, 2009 Report
2007-08 June 14, 2007 Sept. 30, 2007 Report