Milton Building Barrier-Free Access
Contract ID: CT100673
Status
This contract was awarded by Public Works & Services to Energy Efficient Technologies Inc..
The contract is complete.
There were 2 change orders.
Dates
- Start Date
- Mar 31, 2008
- Current End Date
- Sep 30, 2008
- Potential End Date
- Unknown
Description
Construct 2 barrier-free ramps c/w rails and guards. Modify 2 sets of entrance doors. Modify washroom.
Details
- Fiscal Year:
- Buyer:
- Public Works & Services
- Contract Dates:
- to
- Supplier:
- Energy Efficient Technologies Inc.
- Supplier BIP Status:
- BIP Registered
- Supplier Location:
- Fort Simpson
- Original Value:
- $66,458.00
- Change Orders:
- -$11,986.00 (2 changes)
- Current Value:
- $54,472.00
- Community:
- Fort Simpson (Dehcho)
- Process:
- Request for Tenders
- Method:
- Open (Competitive)
- Procurement Type:
- Construction
- Category:
- Building Construction General
- Contract Added:
- Jan. 24, 2018
- Source:
- Contracting Report
Change Orders (Contract Amendments)
Fiscal Year | Change Order Number | Change Order Value |
---|---|---|
2008-09 | 1. cc411789 | (unknown)* |
2008-09 | 2. cc415052 | -$11,986.00 |
* The GNWT only publishes combined change order values so when there are multiple change orders in a fiscal year it is not possible to determine the reason or value for individual change orders.