Boiler Replacement/Conversion, MacKenzie Mountain School, Norman Wells

Contract ID: SC407448
Award dates for non-competitive contracts are not disclosed by the GNWT. Dates below are based on the publishing/tabling of the appropraite Contracting Report.
Status

This contract was awarded by Public Works & Services to A.D. WILLIAMS ENGINEERING INC..

The contract is complete.

There were 0 change orders.

Dates
A rectangle of color grey representing the period of progress A circle of color green representing the start of progress A circle of color red representing the end of progress
Start Date
Jul 25, 2007
Current End Date
Aug 10, 2007
Potential End Date
Unknown

Description

On a rush basis with deadline of August 10th, design ans stamp new fuel oil system to serve replacement School boilers and existing Generator. Replacement boilers and oil storage tanks to be provided by GNWT, with installation of entire project to be by local forces. Installation inspections to be by GNWT staff.

Details

Fiscal Year:
Buyer:
Public Works & Services

Contract Dates:
to

Supplier:
A.D. WILLIAMS ENGINEERING INC.
Supplier BIP Status:
BIP Registered
Supplier Location:
Yellowknife

Original Value:
$10,000.00
Change Orders:
--
Current Value:
$10,000.00

Community:
Norman Wells (Sahtu)
Process:
Sole Source
Method:
Direct
Procurement Type:
Services
Category:
Engineering Consulting

Contract Added:
Jan. 24, 2018
Source:
Contracting Report

Contract Disclosure Report Entries

Fiscal Year Report Period Start Report Period Ending Source
2007-08 April 1, 2007 March 31, 2008 Report