Boiler Replacement/Conversion, MacKenzie Mountain School, Norman Wells
Contract ID: SC407448
Award dates for non-competitive contracts are not disclosed by the GNWT. Dates below are based on the publishing/tabling of the appropraite Contracting Report.
Status
This contract was awarded by Public Works & Services to A.D. WILLIAMS ENGINEERING INC..
The contract is complete.
There were 0 change orders.
Dates
- Start Date
- Jul 25, 2007
- Current End Date
- Aug 10, 2007
- Potential End Date
- Unknown
Description
On a rush basis with deadline of August 10th, design ans stamp new fuel oil system to serve replacement School boilers and existing Generator. Replacement boilers and oil storage tanks to be provided by GNWT, with installation of entire project to be by local forces. Installation inspections to be by GNWT staff.
Details
- Fiscal Year:
- Buyer:
- Public Works & Services
- Contract Dates:
- to
- Supplier:
- A.D. WILLIAMS ENGINEERING INC.
- Supplier BIP Status:
- BIP Registered
- Supplier Location:
- Yellowknife
- Original Value:
- $10,000.00
- Change Orders:
- --
- Current Value:
- $10,000.00
- Community:
- Norman Wells (Sahtu)
- Process:
- Sole Source
- Method:
- Direct
- Procurement Type:
- Services
- Category:
- Engineering Consulting
- Contract Added:
- Jan. 24, 2018
- Source:
- Contracting Report