Labour Services and Equipment for Bridge Rehabilitation
Contract ID: SC791444
Status
This contract was awarded by Transportation to Beaver Enterprises LP.
The contract is complete.
There were 2 change orders.
Dates
- Start Date
- Jul 03, 2007
- Current End Date
- Aug 03, 2007
- Potential End Date
- Unknown
Description
The Contractor is to supply labour services and equipment for the rehabilitation of the following 8 bridge sites on the Liard Highway: Muskeg River km 47.0; Big Island Creek km 65.3; Netla River km 116.0; Creek Bridge km 139.2; Upper Blackstone River km 145.7; Blackstone River km 146.6; Birch River km 201.8 and Poplar River km 219.7.
Details
- Fiscal Year:
- Buyer:
- Transportation
- Contract Dates:
- to
- Supplier:
- Beaver Enterprises LP
- Supplier BIP Status:
- BIP Registered
- Supplier Location:
- Fort Liard
- Original Value:
- $73,650.00
- Change Orders:
- $142,175.18 (2 changes)
- Current Value:
- $215,825.18
- Community:
- Fort Liard (Dehcho)
- Process:
- Request for Tenders
- Method:
- Open (Competitive)
- Procurement Type:
- Services
- Category:
- Labour
- Contract Added:
- Jan. 24, 2018
- Source:
- Contracting Report
Change Orders (Contract Amendments)
Fiscal Year | Change Order Number | Change Order Value |
---|---|---|
2007-08 | 1. CC408950 | $78,475.68 |
2007-08 | 2. CC409184 | $63,699.50 |