Stanton Hospital - Clocks Upgrades
Contract ID: CT100671
Status
This contract was awarded by Public Works & Services to Deer Ridge Electrical Ltd..
The contract is complete.
There were 2 change orders.
Dates
- Start Date
- Apr 01, 2008
- Current End Date
- Mar 20, 2009
- Potential End Date
- Unknown
Description
Documents available through NWT Construction Association by contacting (867) 873-3949. The scope of work includes provision to replace the existing clocks in Stanton Hospital with new ones. Supply & Installation in accordance with the tender documents related to this project.
Details
- Fiscal Year:
- Buyer:
- Public Works & Services
- Contract Dates:
- to
- Supplier:
- Deer Ridge Electrical Ltd.
- Supplier BIP Status:
- BIP Registered
- Supplier Location:
- Yellowknife
- Original Value:
- $89,500.00
- Change Orders:
- $12,954.22 (2 changes)
- Current Value:
- $102,454.22
- Community:
- Yellowknife (North Slave)
- Process:
- Request for Tenders
- Method:
- Open (Competitive)
- Procurement Type:
- Construction
- Category:
- Building Construction General
- Contract Added:
- Jan. 24, 2018
- Source:
- Contracting Report
Change Orders (Contract Amendments)
Fiscal Year | Change Order Number | Change Order Value |
---|---|---|
2008-09 | 1. 415091 | $1,613.10 |
2008-09 | 2. cc413336 | $11,341.12 |
* The GNWT only publishes combined change order values so when there are multiple change orders in a fiscal year it is not possible to determine the reason or value for individual change orders.