Winter Road Construction and Maintenance

Contract ID: CT100708
Status

This contract was awarded by Transportation to MYB Construction Limited.

The contract is complete.

There were 2 change orders.

Dates
A rectangle of color grey representing the period of progress A circle of color green representing the start of progress A circle of color red representing the end of progress
Start Date
Sep 05, 2008
Current End Date
Mar 31, 2013
Potential End Date
Unknown

Description

Construction and maintenance of the winter road over land and frozen bodies of water.

Details

Fiscal Year:
Buyer:
Transportation

Contract Dates:
to

Supplier:
MYB Construction Limited
Supplier BIP Status:
NWT Non-BIP
Supplier Location:
Tulita

Original Value:
$948,975.00
Change Orders:
$773,707.44 (2 changes)
Current Value:
$1,722,682.44

Community:
Deline (Sahtu)
Process:
Request for Proposal
Method:
Open (Competitive)
Procurement Type:
Construction
Category:
Road Construction Services

Contract Added:
Jan. 24, 2018
Source:
Contracting Report

Change Orders (Contract Amendments)

Fiscal Year Change Order Number Change Order Value
2010-11 1. CC425711 $106,400.00
2011-12 2. CC429090 $667,307.44

* The GNWT only publishes combined change order values so when there are multiple change orders in a fiscal year it is not possible to determine the reason or value for individual change orders.

Contract Disclosure Report Entries

Fiscal Year Report Period Start Report Period Ending Source
2008-09 April 1, 2008 March 31, 2009 Report
2010-11 April 1, 2010 March 31, 2011 Report
2011-12 April 1, 2011 March 31, 2012 Report
2008-09 Sept. 5, 2008 March 31, 2013 Report