Fort Providence Campground Picnic Shelter
Contract ID: CT100794
Status
This contract was awarded by Public Works & Services to Mulder Construction.
The contract is complete.
There was 1 change order.
Dates
- Start Date
- Jun 02, 2009
- Current End Date
- Aug 11, 2009
- Potential End Date
- Unknown
Description
Supply and install materials, labor and equipment to construct a Picnic Shelter at Fort Providence Campground. Remove existing structure and dispose off site.
Details
- Fiscal Year:
- Buyer:
- Public Works & Services
- Contract Dates:
- to
- Supplier:
- Mulder Construction
- Supplier BIP Status:
- NWT Non-BIP
- Supplier Location:
- Fort Resolution
- Original Value:
- $97,750.00
- Change Orders:
- $2,650.00 (1 change)
- Current Value:
- $100,400.00
- Community:
- Fort Providence (Dehcho)
- Process:
- Request for Tenders
- Method:
- Open (Competitive)
- Procurement Type:
- Construction
- Category:
- Building Construction General
- Contract Added:
- Jan. 24, 2018
- Source:
- Contracting Report
Change Orders (Contract Amendments)
Fiscal Year | Change Order Number | Change Order Value |
---|---|---|
2009-10 | 1. cc417965 | $2,650.00 |
* The GNWT only publishes combined change order values so when there are multiple change orders in a fiscal year it is not possible to determine the reason or value for individual change orders.