Transformer - Basement Thomas Simpson School

Contract ID: PO095572
Status

This contract was awarded by Public Works & Services to Kiwi Electric Ltd..

The contract is complete.

There were 0 change orders.

Dates
A rectangle of color grey representing the period of progress A circle of color green representing the start of progress A circle of color red representing the end of progress
Start Date
Aug 05, 2009
Current End Date
Aug 05, 2009
Potential End Date
Unknown

Description

Transformer - Basement Thomas Simpson School

Details

Fiscal Year:
Buyer:
Public Works & Services

Contract Dates:
to

Supplier:
Kiwi Electric Ltd.
Supplier BIP Status:
BIP Registered
Supplier Location:
Fort Simpson

Original Value:
$5,585.95
Change Orders:
--
Current Value:
$5,585.95

Community:
Fort Simpson (Dehcho)
Process:
Request for Tenders
Method:
Open (Competitive)
Procurement Type:
Goods
Category:
Building Construction Materials

Contract Added:
Jan. 24, 2018
Source:
Contracting Report

Contract Disclosure Report Entries

Fiscal Year Report Period Start Report Period Ending Source
2009-10 April 1, 2009 March 31, 2010 Report
2009-10 Aug. 5, 2009 Aug. 5, 2009 Report