BUILDING ENVELOPE THERMOGRAPHIC INVESTIGATION

Contract ID: SC792532
Status

This contract was awarded by Public Works & Services to Williams Engineering Canada.

The contract is complete.

There were 0 change orders.

Dates
A rectangle of color grey representing the period of progress A circle of color green representing the start of progress A circle of color red representing the end of progress
Start Date
Nov 23, 2009
Current End Date
Dec 11, 2009
Potential End Date
Unknown

Description

Provision of consultant services to perform a thermographic survey of the Chief Albert Wright School building envelope in Tulita, NT.

Details

Fiscal Year:
Buyer:
Public Works & Services

Contract Dates:
to

Supplier:
Williams Engineering Canada
Supplier BIP Status:
BIP Registered
Supplier Location:
Yellowknife

Original Value:
$8,660.00
Change Orders:
--
Current Value:
$8,660.00

Community:
Tulita (Sahtu)
Process:
Request for Proposal
Method:
Open (Competitive)
Procurement Type:
Services
Category:
Consulting Services - General

Contract Added:
Jan. 24, 2018
Source:
Contracting Report

Contract Disclosure Report Entries

Fiscal Year Report Period Start Report Period Ending Source
2009-10 April 1, 2009 March 31, 2010 Report
2009-10 Nov. 23, 2009 Dec. 11, 2009 Report