Supervision and Inspection of Drainage Ditch Construction

Contract ID: SC792586
Award dates for non-competitive contracts are not disclosed by the GNWT. Dates below are based on the publishing/tabling of the appropraite Contracting Report.
Status

This contract was awarded by Transportation to Aboriginal Engineering Ltd.

The contract is complete.

There were 0 change orders.

Dates
A rectangle of color grey representing the period of progress A circle of color green representing the start of progress A circle of color red representing the end of progress
Start Date
Oct 15, 2009
Current End Date
Nov 06, 2009
Potential End Date
Unknown

Description

Supervision and Inspection of Drainage Ditch Construction at Nahanni Butte Airport

Details

Fiscal Year:
Buyer:
Transportation

Contract Dates:
to

Supplier:
Aboriginal Engineering Ltd
Supplier BIP Status:
BIP Registered
Supplier Location:
Yellowknife

Original Value:
$21,322.80
Change Orders:
--
Current Value:
$21,322.80

Community:
Nahanni Butte (Dehcho)
Process:
Sole Source
Method:
Direct
Procurement Type:
Services
Category:
Engineering Consulting

Contract Added:
Jan. 24, 2018
Source:
Contracting Report

Contract Disclosure Report Entries

Fiscal Year Report Period Start Report Period Ending Source
2009-10 April 1, 2009 March 31, 2010 Report
2009-10 Oct. 15, 2009 Nov. 6, 2009 Report