Supply and Install Concrete Barriers

Contract ID: SC792958
Status

This contract was awarded by Transportation to Beaver Enterprises LP.

The contract is complete.

There were 0 change orders.

Dates
A rectangle of color grey representing the period of progress A circle of color green representing the start of progress A circle of color red representing the end of progress
Start Date
Aug 23, 2010
Current End Date
Aug 30, 2010
Potential End Date
Unknown

Description

The Contractor shall supply and install three (3) pre-cast concrete barriers, and one (1) end treatment at Km 5.2 on Highway No. 7. The Contractor shall also remove the two (2) exisiting barriers and deliver to the Power Corp. location in Ft. Liard.

Details

Fiscal Year:
Buyer:
Transportation

Contract Dates:
to

Supplier:
Beaver Enterprises LP
Supplier BIP Status:
BIP Registered
Supplier Location:
Fort Liard

Original Value:
$5,080.40
Change Orders:
--
Current Value:
$5,080.40

Community:
Fort Liard (Dehcho)
Process:
Request for Tenders
Method:
Open (Competitive)
Procurement Type:
Services
Category:
Highway Maintenance

Contract Added:
Jan. 24, 2018
Source:
Contracting Report

Contract Disclosure Report Entries

Fiscal Year Report Period Start Report Period Ending Source
2010-11 April 1, 2010 March 31, 2011 Report
2010-11 Aug. 23, 2010 Aug. 30, 2010 Report