Fuel Tank Levelling

Contract ID: SC793459
Award dates for non-competitive contracts are not disclosed by the GNWT. Dates below are based on the publishing/tabling of the appropraite Contracting Report.
Status

This contract was awarded by Transportation to Kingland Freightliner.

The contract is complete.

There were 0 change orders.

Dates
A rectangle of color grey representing the period of progress A circle of color green representing the start of progress A circle of color red representing the end of progress
Start Date
Jun 22, 2011
Current End Date
Jul 31, 2011
Potential End Date
Unknown

Description

To comply with Petroleum Products Division standards, two fuel tanks in Trout Lake need to be set on treated lumber pads to distribute the bearing load of the tank and its contents over a larger area.

Details

Fiscal Year:
Buyer:
Transportation

Contract Dates:
to

Supplier:
Kingland Freightliner
Supplier BIP Status:
NWT Non-BIP
Supplier Location:
Hay River

Original Value:
$108,627.20
Change Orders:
--
Current Value:
$108,627.20

Community:
Sambaa K'e (Dehcho)
Process:
Sole Source
Method:
Direct
Procurement Type:
Services
Category:
Remediation Services - Environmental/ Engineering Services

Contract Added:
Jan. 24, 2018
Source:
Contracting Report

Contract Disclosure Report Entries

Fiscal Year Report Period Start Report Period Ending Source
2011-12 April 1, 2011 March 31, 2012 Report
2011-12 June 22, 2011 July 31, 2011 Report