Automatic Sliding Door Installation

Contract ID: SC793521
Status

This contract was awarded by Public Works & Services to C&L Holdings Ltd..

The contract is complete.

There were 0 change orders.

Dates
A rectangle of color grey representing the period of progress A circle of color green representing the start of progress A circle of color red representing the end of progress
Start Date
Aug 25, 2011
Current End Date
Oct 31, 2011
Potential End Date
Unknown

Description

Supply and install automatic sliding door at the Fort Smith Airport terminal.

Details

Fiscal Year:
Buyer:
Public Works & Services

Contract Dates:
to

Supplier:
C&L Holdings Ltd.
Supplier BIP Status:
BIP Registered
Supplier Location:
Fort Smith

Original Value:
$93,458.00
Change Orders:
--
Current Value:
$93,458.00

Community:
Fort Smith (South Slave)
Process:
Request for Tenders
Method:
Open (Competitive)
Procurement Type:
Construction
Category:
Building Construction General

Contract Added:
Jan. 24, 2018
Source:
Contracting Report

Contract Disclosure Report Entries

Fiscal Year Report Period Start Report Period Ending Source
2011-12 April 1, 2011 March 31, 2012 Report
2011-12 Aug. 25, 2011 Oct. 31, 2011 Report