ENR warehouse roofing repairs

Contract ID: SC793752
Award dates for non-competitive contracts are not disclosed by the GNWT. Dates below are based on the publishing/tabling of the appropraite Contracting Report.
Status

This contract was awarded by Public Works & Services to Pete Rose's Welding Ltd.

The contract is complete.

There were 0 change orders.

Dates
A rectangle of color grey representing the period of progress A circle of color green representing the start of progress A circle of color red representing the end of progress
Start Date
Oct 12, 2011
Current End Date
Nov 04, 2011
Potential End Date
Unknown

Description

Repairning the roof of the ENR warehouse in Norman Wells, icluding the supply and delivery of the materials.

Details

Fiscal Year:
Buyer:
Public Works & Services

Contract Dates:
to

Supplier:
Pete Rose's Welding Ltd
Supplier BIP Status:
BIP Registered
Supplier Location:
Norman Wells

Original Value:
$9,500.00
Change Orders:
--
Current Value:
$9,500.00

Community:
Norman Wells (Sahtu)
Process:
Sole Source
Method:
Direct
Procurement Type:
Services
Category:
Roofing/Shingling

Contract Added:
Jan. 24, 2018
Source:
Contracting Report

Contract Disclosure Report Entries

Fiscal Year Report Period Start Report Period Ending Source
2011-12 April 1, 2011 March 31, 2012 Report
2011-12 Oct. 12, 2011 Nov. 4, 2011 Report