Bob's Canyon Crossing & Strawberry Creek Crossing

Contract ID: CT101252
Status

This contract was awarded by Transportation to Pedzeh Ki Contractors Limited.

The contract is complete.

There were 4 change orders.

Dates
A rectangle of color grey representing the period of progress A circle of color green representing the start of progress A circle of color red representing the end of progress
Start Date
Oct 01, 2012
Current End Date
Apr 30, 2014
Potential End Date
Unknown

Description

Install 3 bridge-plate Arch Culverts and build new road alignments at the two crossing sites.

Details

Fiscal Year:
Buyer:
Transportation

Contract Dates:
to

Supplier:
Pedzeh Ki Contractors Limited
Supplier BIP Status:
BIP Registered
Supplier Location:
Wrigley

Original Value:
$4,000,000.00
Change Orders:
$668,187.20 (4 changes)
Current Value:
$4,668,187.20

Community:
Wrigley (Dehcho)
Process:
Negotiated
Method:
Direct
Procurement Type:
Construction
Category:
Road Construction Services

Contract Added:
Jan. 24, 2018
Source:
Contracting Report

Change Orders (Contract Amendments)

Fiscal Year Change Order Number Change Order Value
2013-14 1. CC438851 $769,492.80
2013-14 2. CC439228 $127,759.50
2014-15 3. CC440488 (unknown)*
2014-15 4. CC440727 -$229,065.10

* The GNWT only publishes combined change order values so when there are multiple change orders in a fiscal year it is not possible to determine the reason or value for individual change orders.

Contract Disclosure Report Entries

Fiscal Year Report Period Start Report Period Ending Source
2012-13 April 1, 2012 March 31, 2013 Report
2013-14 April 1, 2013 March 31, 2014 Report
2012-13 Oct. 1, 2012 Nov. 1, 2013 Report