Tuktoyaktuk to Granular Source 177 Access Road Upgrade Km 1.55 To Km 20.02
Contract ID: CT101281
Status
This contract was awarded by Transportation to EGT Northwind Ltd..
The contract is complete.
There were 2 change orders.
Dates
- Start Date
- Mar 18, 2013
- Current End Date
- Nov 30, 2014
- Potential End Date
- Unknown
Description
The Contract consists of borrow excavation common: 472,000 cubic metres Supply and installation of Non-wowen Geotextile Fabric Armtec 350 or equivelent: 140,000 square metres Supply and installation of CSP culverts:520 lineal metres Surveying and Engineering c/w Layout, Cross Section Data Complete with Construction Surveying, Quantity Control, Quality Control, all Soil Testing
Details
- Fiscal Year:
- Buyer:
- Transportation
- Contract Dates:
- to
- Supplier:
- EGT Northwind Ltd.
- Supplier BIP Status:
- NWT Non-BIP
- Supplier Location:
- Tuktoyaktuk
- Original Value:
- $18,313,655.00
- Change Orders:
- $149,500.00 (2 changes)
- Current Value:
- $18,463,155.00
- Community:
- <Various Communities>
- Process:
- Negotiated
- Method:
- Direct
- Procurement Type:
- Construction
- Category:
- Road Construction Services
- Contract Added:
- Jan. 24, 2018
- Source:
- Contracting Report
Change Orders (Contract Amendments)
Fiscal Year | Change Order Number | Change Order Value |
---|---|---|
2013-14 | 1. CC435720 | $92,300.00 |
2014-15 | 2. CC445540 | $57,200.00 |
* The GNWT only publishes combined change order values so when there are multiple change orders in a fiscal year it is not possible to determine the reason or value for individual change orders.