2012 Overflow Parking Lot Paving

Contract ID: PO001283
Award dates for non-competitive contracts are not disclosed by the GNWT. Dates below are based on the publishing/tabling of the appropraite Contracting Report.
Status

This contract was awarded by Assembly to NWT CONSTRUCTION.

The contract is complete.

There were 0 change orders.

Dates
A rectangle of color grey representing the period of progress A circle of color green representing the start of progress A circle of color red representing the end of progress
Start Date
Aug 20, 2012
Current End Date
Sep 21, 2012
Potential End Date
Unknown

Description

Overflow Parking Lot Paving

Details

Fiscal Year:
Buyer:
Assembly

Contract Dates:
to

Supplier:
NWT CONSTRUCTION
Supplier BIP Status:
BIP Registered
Supplier Location:
Yellowknife

Original Value:
$68,991.00
Change Orders:
--
Current Value:
$68,991.00

Community:
Yellowknife (North Slave)
Process:
Sole Source
Method:
Direct
Procurement Type:
Construction
Category:
Road Construction Services

Contract Added:
Jan. 24, 2018
Source:
Contracting Report

Contract Disclosure Report Entries

Fiscal Year Report Period Start Report Period Ending Source
2012-13 April 1, 2012 March 31, 2013 Report
2012-13 Aug. 20, 2012 Sept. 21, 2012 Report