Blueprint Planning - FMA Implementation

Contract ID: SC439411
Award dates for non-competitive contracts are not disclosed by the GNWT. Dates below are based on the publishing/tabling of the appropraite Contracting Report.
Status

This contract was awarded by Environment and Natural Resources to MNP Winnipeg.

The contract is complete.

There were 0 change orders.

Dates
A rectangle of color grey representing the period of progress A circle of color green representing the start of progress A circle of color red representing the end of progress
Start Date
Mar 10, 2014
Current End Date
Jun 30, 2014
Potential End Date
Unknown

Description

Blueprint Planning - FMA Implementation

Details

Fiscal Year:
Buyer:
Environment and Natural Resources

Contract Dates:
to

Supplier:
MNP Winnipeg
Supplier BIP Status:
Not in NWT
Supplier Location:
Edmonton

Original Value:
$32,000.00
Change Orders:
--
Current Value:
$32,000.00

Community:
Fort Smith (South Slave)
Process:
Sole Source
Method:
Direct
Procurement Type:
Services
Category:
Consulting Services - General

Contract Added:
Jan. 24, 2018
Source:
Contracting Report

Contract Disclosure Report Entries

Fiscal Year Report Period Start Report Period Ending Source
2013-14 April 1, 2013 March 31, 2014 Report
2013-14 March 10, 2014 June 30, 2014 Report