Engineering Consulting Services

Contract ID: SC794507
Award dates for non-competitive contracts are not disclosed by the GNWT. Dates below are based on the publishing/tabling of the appropraite Contracting Report.
Status

This contract was awarded by Transportation to Wood Environment & Infrastructure.

The contract is complete.

There were 0 change orders.

Dates
A rectangle of color grey representing the period of progress A circle of color green representing the start of progress A circle of color red representing the end of progress
Start Date
Aug 26, 2013
Current End Date
Dec 06, 2013
Potential End Date
Unknown

Description

Contractor shall provide Engineering support services on the Inuvik to Tuktoyaktuk Highway (ITH) Project, as owner's representative for first phase of the project.

Details

Fiscal Year:
Buyer:
Transportation

Contract Dates:
to

Supplier:
Wood Environment & Infrastructure
Supplier BIP Status:
NWT Non-BIP
Supplier Location:
Yellowknife

Original Value:
$239,380.00
Change Orders:
--
Current Value:
$239,380.00

Community:
Inuvik (Beaufort-Delta)
Process:
SOA Release (Master SOA: SO050847)
Method:
Selective (Prequalified)
This is a Standing Offer Agreement (SOA) Release, which means it has been contracted under the terms of an existing Standing Offer agreement. The GNWT does not generally track or disclose which agreement these releases are related to.However, in this case, we know the master agreement is SO050847.
Procurement Type:
Services
Category:
Engineering Consulting

Contract Added:
Jan. 24, 2018
Source:
Contracting Report

Contract Disclosure Report Entries

Fiscal Year Report Period Start Report Period Ending Source
2013-14 April 1, 2013 March 31, 2014 Report
2013-14 Aug. 26, 2013 Dec. 6, 2013 Report