Professional Engineering Site Services - Steep Creek Bridge

Contract ID: SC794850
Award dates for non-competitive contracts are not disclosed by the GNWT. Dates below are based on the publishing/tabling of the appropraite Contracting Report.
Status

This contract was awarded by Transportation to Associated Engineering Ltd..

The contract is complete.

There were 0 change orders.

Dates
A rectangle of color grey representing the period of progress A circle of color green representing the start of progress A circle of color red representing the end of progress
Start Date
Feb 25, 2014
Current End Date
Mar 31, 2014
Potential End Date
Unknown

Description

Professional Engineering Site Services - Steep Creek Bridge Backwall Rehabilitation

Details

Fiscal Year:
Buyer:
Transportation

Contract Dates:
to

Supplier:
Associated Engineering Ltd.
Supplier BIP Status:
Not in NWT
Supplier Location:
Burnaby

Original Value:
$46,848.19
Change Orders:
--
Current Value:
$46,848.19

Community:
Wrigley (Dehcho)
Process:
Sole Source
Method:
Direct
Procurement Type:
Construction (Contract Type: Services)
Category:
Engineering Consulting

Contract Added:
Jan. 24, 2018
Source:
Contracting Report

Contract Disclosure Report Entries

Fiscal Year Report Period Start Report Period Ending Source
2013-14 April 1, 2013 March 31, 2014 Report
2013-14 Feb. 25, 2014 March 31, 2014 Report