MVH Economic Analysis and Business Case

Contract ID: SC445160
Award dates for non-competitive contracts are not disclosed by the GNWT. Dates below are based on the publishing/tabling of the appropraite Contracting Report.
Status

This contract was awarded by Transportation to Nichols Applied Management.

The contract is complete.

There was 1 change order.

Dates
A rectangle of color grey representing the period of progress A circle of color green representing the start of progress A circle of color red representing the end of progress
Start Date
Oct 28, 2014
Current End Date
Mar 31, 2015
Potential End Date
Unknown

Description

1. Develop an economic analysis to strengthen the business case for the GNWT Mackenzie Valley Highway (MVH) segment from Wrigley to Norman Wells under the NBCP National Infrastructure Component (NIC). 2. Develop a business case for the GNWT application to the federal government under the New Building Canada Plan (NBCP) Provincial/Territorial Infrastructure Component (PTIC).

Details

Fiscal Year:
Buyer:
Transportation

Contract Dates:
to

Supplier:
Nichols Applied Management
Supplier BIP Status:
Not in NWT
Supplier Location:
Edmonton

Original Value:
$57,500.00
Change Orders:
-- (1 change)
Current Value:
$57,500.00

Community:
Yellowknife (North Slave)
Process:
Sole Source
Method:
Direct
Procurement Type:
Services
Category:
Consulting Services - General

Contract Added:
Jan. 24, 2018
Source:
Contracting Report

Change Orders (Contract Amendments)

Fiscal Year Change Order Number Change Order Value
2014-15 1. CC446447 (unknown)*

* The GNWT only publishes combined change order values so when there are multiple change orders in a fiscal year it is not possible to determine the reason or value for individual change orders.

Contract Disclosure Report Entries

Fiscal Year Report Period Start Report Period Ending Source
2014-15 April 1, 2014 March 31, 2015 Report
2014-15 Oct. 28, 2014 Nov. 27, 2014 Report