Ice Road Construction

Contract ID: SC794887
Award dates for non-competitive contracts are not disclosed by the GNWT. Dates below are based on the publishing/tabling of the appropraite Contracting Report.
Status

This contract was awarded by Transportation to Naha Dehe Development Corporation.

The contract is complete.

There were 0 change orders.

Dates
A rectangle of color grey representing the period of progress A circle of color green representing the start of progress A circle of color red representing the end of progress
Start Date
Apr 01, 2014
Current End Date
Mar 31, 2015
Potential End Date
Unknown

Description

Construction of the Ice Bridge

Details

Fiscal Year:
Buyer:
Transportation

Contract Dates:
to

Supplier:
Naha Dehe Development Corporation
Supplier BIP Status:
NWT Non-BIP
Supplier Location:
Nahanni Butte

Original Value:
$19,000.00
Change Orders:
--
Current Value:
$19,000.00

Community:
Nahanni Butte (Dehcho)
Process:
Sole Source
Method:
Direct
Procurement Type:
Construction
Category:
Road Construction Services

Contract Added:
Jan. 24, 2018
Source:
Contracting Report

Contract Disclosure Report Entries

Fiscal Year Report Period Start Report Period Ending Source
2014-15 April 1, 2014 March 31, 2015 Report
2014-15 April 1, 2014 March 31, 2015 Report