SO438661 - Flooring - NSRO

Contract ID: WO264617
Award dates for non-competitive contracts are not disclosed by the GNWT. Dates below are based on the publishing/tabling of the appropraite Contracting Report.
Status

This contract was awarded by Public Works & Services to Elite Commercial Flooring.

The contract is complete.

There were 0 change orders.

Dates
A rectangle of color grey representing the period of progress A circle of color green representing the start of progress A circle of color red representing the end of progress
Start Date
Jul 07, 2014
Current End Date
Aug 21, 2014
Potential End Date
Unknown

Description

SO438661 - Flooring - NSRO. Supply and install new flooring and base in the daycare area at Ecole Allain St Cyr School in Yellowknife. Invoice #2072

Details

Fiscal Year:
Buyer:
Public Works & Services

Contract Dates:
to

Supplier:
Elite Commercial Flooring
Supplier BIP Status:
BIP Registered
Supplier Location:
Yellowknife

Original Value:
$8,376.00
Change Orders:
--
Current Value:
$8,376.00

Community:
Yellowknife (North Slave)
Process:
SOA Release (Master SOA: SO438661)
Method:
Selective (Prequalified)
This is a Standing Offer Agreement (SOA) Release, which means it has been contracted under the terms of an existing Standing Offer agreement. The GNWT does not generally track or disclose which agreement these releases are related to.However, in this case, we know the master agreement is SO438661.
Procurement Type:
Services
Category:
Floor Covering

Contract Added:
Jan. 24, 2018
Source:
Contracting Report

Contract Disclosure Report Entries

Fiscal Year Report Period Start Report Period Ending Source
2014-15 April 1, 2014 March 31, 2015 Report
2014-15 July 7, 2014 Aug. 21, 2014 Report