Supply, Ship, & Erect

Contract ID: PM008883
Status

This contract was awarded by NWT Housing Corporation to John Bjornson Construction Ltd..

The contract is complete.

There was 1 change order.

Dates
A rectangle of color grey representing the period of progress A circle of color green representing the start of progress A circle of color red representing the end of progress
Start Date
Nov 03, 2009
Current End Date
Mar 25, 2010
Potential End Date
Unknown

Description

2009/2010 M&I - SSE - Insulate & install siding (2-units)

Details

Fiscal Year:
Buyer:
NWT Housing Corporation

Contract Dates:
to

Supplier:
John Bjornson Construction Ltd.
Supplier BIP Status:
BIP Registered
Supplier Location:
Fort Resolution

Original Value:
$32,500.00
Change Orders:
$3,500.00 (1 change)
Current Value:
$36,000.00

Community:
Fort Resolution (South Slave)
Process:
Request for Tenders
Method:
Open (Competitive)
Procurement Type:
Services
Category:
Building Maintenance

Contract Added:
Jan. 24, 2018
Source:
Contracting Report

Change Orders (Contract Amendments)

Fiscal Year Change Order Number Change Order Value
2009-10 1. CA100449 $3,500.00

* The GNWT only publishes combined change order values so when there are multiple change orders in a fiscal year it is not possible to determine the reason or value for individual change orders.

Contract Disclosure Report Entries

Fiscal Year Report Period Start Report Period Ending Source
2009-10 April 1, 2009 March 31, 2010 Report
2009-10 Nov. 3, 2009 Jan. 31, 2010 Report