2010/2011 CARE Home Repair - One Client

Contract ID: SC570289
Status

This contract was awarded by NWT Housing Corporation to GBM Construction.

The contract is complete.

There were 2 change orders.

Dates
A rectangle of color grey representing the period of progress A circle of color green representing the start of progress A circle of color red representing the end of progress
Start Date
Jun 30, 2010
Current End Date
Oct 30, 2010
Potential End Date
Unknown

Description

2010/2011 CARE Home Repair - One Client

Details

Fiscal Year:
Buyer:
NWT Housing Corporation

Contract Dates:
to

Supplier:
GBM Construction
Supplier BIP Status:
NWT Non-BIP
Supplier Location:
Fort Simpson

Original Value:
$63,000.00
Change Orders:
-- (2 changes)
Current Value:
$63,000.00

Community:
Fort Simpson (Dehcho)
Process:
Request for Tenders
Method:
Open (Competitive)
Procurement Type:
Construction
Category:
Building Construction General

Contract Added:
Jan. 24, 2018
Source:
Contracting Report

Change Orders (Contract Amendments)

Fiscal Year Change Order Number Change Order Value
2010-11 1. CA00000001 (unknown)*
2010-11 2. CA530002 (unknown)*

* The GNWT only publishes combined change order values so when there are multiple change orders in a fiscal year it is not possible to determine the reason or value for individual change orders.

Contract Disclosure Report Entries

Fiscal Year Report Period Start Report Period Ending Source
2010-11 April 1, 2010 March 31, 2011 Report
2010-11 June 30, 2010 Sept. 15, 2010 Report