Labour Only

Contract ID: SC580296
Status

This contract was awarded by NWT Housing Corporation to Deline Construction Ltd..

The contract is complete.

There was 1 change order.

Dates
A rectangle of color grey representing the period of progress A circle of color green representing the start of progress A circle of color red representing the end of progress
Start Date
Aug 03, 2010
Current End Date
Mar 18, 2013
Potential End Date
Unknown

Description

2010-2011 Various repairs (interior/ exterior) for one (1) house Client #2722

Details

Fiscal Year:
Buyer:
NWT Housing Corporation

Contract Dates:
to

Supplier:
Deline Construction Ltd.
Supplier BIP Status:
BIP Registered
Supplier Location:
Deline

Original Value:
$24,500.00
Change Orders:
-$1,500.00 (1 change)
Current Value:
$23,000.00

Community:
Norman Wells (Sahtu)
Process:
Request for Tenders
Method:
Open (Competitive)
Procurement Type:
Construction
Category:
Building Construction General

Contract Added:
Jan. 24, 2018
Source:
Contracting Report

Change Orders (Contract Amendments)

Fiscal Year Change Order Number Change Order Value
2012-13 1. CA103098 -$1,500.00

* The GNWT only publishes combined change order values so when there are multiple change orders in a fiscal year it is not possible to determine the reason or value for individual change orders.

Contract Disclosure Report Entries

Fiscal Year Report Period Start Report Period Ending Source
2010-11 April 1, 2010 March 31, 2011 Report
2010-11 Aug. 3, 2010 Nov. 30, 2010 Report