2012/2013 - SSE - Structural Floor Repair

Contract ID: SC520939
Status

This contract was awarded by NWT Housing Corporation to KP Woodwright Ltd..

The contract is complete.

There was 1 change order.

Dates
A rectangle of color grey representing the period of progress A circle of color green representing the start of progress A circle of color red representing the end of progress
Start Date
Nov 19, 2012
Current End Date
Mar 31, 2013
Potential End Date
Unknown

Description

2012/2013 - SSE - Structural Floor Repair

Details

Fiscal Year:
Buyer:
NWT Housing Corporation

Contract Dates:
to

Supplier:
KP Woodwright Ltd.
Supplier BIP Status:
BIP Registered
Supplier Location:
Hay River

Original Value:
$9,494.00
Change Orders:
$500.00 (1 change)
Current Value:
$9,994.00

Community:
Hay River Reserve (South Slave)
Process:
Request for Tenders
Method:
Open (Competitive)
Procurement Type:
Construction
Category:
Building Construction General

Contract Added:
Jan. 24, 2018
Source:
Contracting Report

Change Orders (Contract Amendments)

Fiscal Year Change Order Number Change Order Value
2012-13 1. CA5722 $500.00

* The GNWT only publishes combined change order values so when there are multiple change orders in a fiscal year it is not possible to determine the reason or value for individual change orders.

Contract Disclosure Report Entries

Fiscal Year Report Period Start Report Period Ending Source
2012-13 April 1, 2012 March 31, 2013 Report
2012-13 Nov. 19, 2012 Dec. 31, 2012 Report