2012-13 M & I, Supply, Ship & Erect, #9 Marten Avenue

Contract ID: SC580432
Status

This contract was awarded by NWT Housing Corporation to Harold Construction.

The contract is complete.

There were 2 change orders.

Dates
A rectangle of color grey representing the period of progress A circle of color green representing the start of progress A circle of color red representing the end of progress
Start Date
Jan 04, 2013
Current End Date
Jul 31, 2013
Potential End Date
Unknown

Description

Scope of work to include but not be limited to exterior staining, replace interior and exterior doors, patching and painting throughout, cleaning and waxing floors, cleaning all appliances, windows, painting all trim work around doors and windows, painting baseboards, servicing boiler, replace damaged/missing lights, coverplates, replacing bathroom complete including repairing floor, replacing living room ceiling light fixtures and installing LED light bulbs equivilant to 60 watt bulbs.

Details

Fiscal Year:
Buyer:
NWT Housing Corporation

Contract Dates:
to

Supplier:
Harold Construction
Supplier BIP Status:
BIP Registered
Supplier Location:
Norman Wells

Original Value:
$57,000.00
Change Orders:
$8,500.00 (2 changes)
Current Value:
$65,500.00

Community:
Norman Wells (Sahtu)
Process:
Request for Tenders
Method:
Open (Competitive)
Procurement Type:
Construction
Category:
Building Construction General

Contract Added:
Jan. 24, 2018
Source:
Contracting Report

Change Orders (Contract Amendments)

Fiscal Year Change Order Number Change Order Value
2012-13 1. CA102827 $6,500.00
2013-14 2. CA103099 $2,000.00

* The GNWT only publishes combined change order values so when there are multiple change orders in a fiscal year it is not possible to determine the reason or value for individual change orders.

Contract Disclosure Report Entries

Fiscal Year Report Period Start Report Period Ending Source
2012-13 April 1, 2012 March 31, 2013 Report
2012-13 Jan. 4, 2013 July 31, 2013 Report