2012/2013 - SSE - Fuel Tank Replacement

Contract ID: SC520943
Status

This contract was awarded by NWT Housing Corporation to John Bjornson Construction Ltd..

The contract is complete.

There were 0 change orders.

Dates
A rectangle of color grey representing the period of progress A circle of color green representing the start of progress A circle of color red representing the end of progress
Start Date
Dec 19, 2012
Current End Date
Dec 31, 2012
Potential End Date
Unknown

Description

2012/2013 - SSE - Fuel Tank Replacement For Tender Documents please E-mail [email protected]

Details

Fiscal Year:
Buyer:
NWT Housing Corporation

Contract Dates:
to

Supplier:
John Bjornson Construction Ltd.
Supplier BIP Status:
BIP Registered
Supplier Location:
Fort Resolution

Original Value:
$5,000.00
Change Orders:
--
Current Value:
$5,000.00

Community:
Fort Resolution (South Slave)
Process:
Request for Tenders
Method:
Open (Competitive)
Procurement Type:
Construction
Category:
Building Construction General

Contract Added:
Jan. 24, 2018
Source:
Contracting Report

Contract Disclosure Report Entries

Fiscal Year Report Period Start Report Period Ending Source
2012-13 April 1, 2012 March 31, 2013 Report
2012-13 Dec. 19, 2012 Dec. 31, 2012 Report