2013/2014 - SSE - Interior/Exterior Repairs & Upgrades

Contract ID: SC520958
Status

This contract was awarded by NWT Housing Corporation to Alex L. Sunrise Home Improvements.

The contract is complete.

There were 2 change orders.

Dates
A rectangle of color grey representing the period of progress A circle of color green representing the start of progress A circle of color red representing the end of progress
Start Date
Jul 29, 2013
Current End Date
Nov 29, 2013
Potential End Date
Unknown

Description

2013/2014 - SSE - Interior/Exterior Repairs & Upgrades

Details

Fiscal Year:
Buyer:
NWT Housing Corporation

Contract Dates:
to

Supplier:
Alex L. Sunrise Home Improvements
Supplier BIP Status:
BIP Registered
Supplier Location:
Hay River

Original Value:
$71,300.00
Change Orders:
-$5,100.00 (2 changes)
Current Value:
$66,200.00

Community:
Hay River Reserve (South Slave)
Process:
Request for Tenders
Method:
Open (Competitive)
Procurement Type:
Construction
Category:
Building Construction General

Contract Added:
Jan. 24, 2018
Source:
Contracting Report

Change Orders (Contract Amendments)

Fiscal Year Change Order Number Change Order Value
2013-14 1. CA7890 -$7,300.00
2013-14 2. CA7897 $2,200.00

* The GNWT only publishes combined change order values so when there are multiple change orders in a fiscal year it is not possible to determine the reason or value for individual change orders.

Contract Disclosure Report Entries

Fiscal Year Report Period Start Report Period Ending Source
2013-14 April 1, 2013 March 31, 2014 Report
2013-14 July 29, 2013 Oct. 31, 2013 Report