MHU M&I SSE UNIT #3024001, Fort Good Hope, NT,
Contract ID: SC441242
Status
This contract was awarded by NWT Housing Corporation to Green Tree Enterprises Ltd..
The contract is complete.
There was 1 change order.
Dates
- Start Date
- Feb 12, 2015
- Current End Date
- Aug 12, 2015
- Potential End Date
- Unknown
Description
Please refer to tender documents for scope and other terms & conditions: 1-Level the entire unit. 2-Ensure all foundation pads are installed level and are stable. 3-Ensure all foundation blocks and wedges are installed as per specifications and are operating as intended. 4-Check and replace any deteriorated foundation wood components. 5-Repair the existing plywood skirting and ensure it is a minimum of 6” above the ground level. 6-The skirting shall be framed with 2 x 4 lumber installed 16” on center and braces provided. 7-Check and repair any skirting plywood that is damaged. 8-Stain with 2 coats of exterior stain all skirting plywood. Stain color to be similar to the original color. 9-Install a layer of R-12 insulation within the entire interior cavity of the skirting. The insulation shall be secured to the skirting with staples. 10-Install a layer of 6 Mil. poly over the entire skirting insulation. The poly should be installed with a minimum of 16” lying on the ground and a minimum of 12 inches to be attached to the belly bag of the mobile unit. 11-Build and install an insulated door within the skirting. Check with the housing Association for the location of the door. 12-Build and compact a gravel pad with a minimum thickness of 16” above surrounding ground area. 13-The pad dimensions shall be 14 feet wide by 20 feet deep to accommodate a 10 feet by 16 feet wood storage shed. 14-Build and install a 10 feet by 16 feet storage shed as per drawing and specifications. See annex #1 for details. 15-Check the condition of the existing house landing, remove any deteriorated lumber and replace with new lumber. 16-Remove the existing stair case completely. 17-Please refer to tender documents for detailed scope of work.
Details
- Fiscal Year:
- Buyer:
- NWT Housing Corporation
- Contract Dates:
- to
- Supplier:
- Green Tree Enterprises Ltd.
- Supplier BIP Status:
- BIP Registered
- Supplier Location:
- Fort Good Hope
- Original Value:
- $99,000.00
- Change Orders:
- $200.00 (1 change)
- Current Value:
- $99,200.00
- Community:
- Fort Good Hope (Sahtu)
- Process:
- Request for Tenders
- Method:
- Open (Competitive)
- Procurement Type:
- Construction
- Category:
- Building Construction General
- Contract Added:
- Jan. 24, 2018
- Source:
- Contracting Report
Change Orders (Contract Amendments)
Fiscal Year | Change Order Number | Change Order Value |
---|---|---|
2015-16 | 1. CA102719 | $200.00 |
* The GNWT only publishes combined change order values so when there are multiple change orders in a fiscal year it is not possible to determine the reason or value for individual change orders.