SSE, Market Housing Unit, Floor Replacement Unit 11 A/B; 13 B Mount Avens Court

Contract ID: SC441339
Status

This contract was awarded by NWT Housing Corporation to Harold Construction.

The contract is complete.

There were 0 change orders.

Dates
A rectangle of color grey representing the period of progress A circle of color green representing the start of progress A circle of color red representing the end of progress
Start Date
Jul 07, 2015
Current End Date
Aug 31, 2015
Potential End Date
Unknown

Description

Remove all carpet and foam padding from living room and bedrooms, remove baseboard, install new U-lay, approx. 400 sq.ft., prepare for installation of foam backing and laminate flooring. Remove linoleum from entry and prepare floor to install new linoleum floor covering, including transition strips at utility. Install new transition strip in kitchen/ living room at lino/ laminate floor. Re-install removed baseboards and fill nail holes.

Details

Fiscal Year:
Buyer:
NWT Housing Corporation
Reported Contract Buyer:

Contract Dates:
to

Supplier:
Harold Construction
Supplier BIP Status:
--
Supplier Location:
Norman Wells , NT

Original Value:
$27,340.00
Change Orders:
--
Final Value:
$27,340.00

Community:
--
Process:
Request for Tenders
Method:
Open (Competitive)
Procurement Type:
Construction
Category:
--

Contract Added:
Feb. 1, 2024
Source:
CRRS Extract

Contract Disclosure Report Entries

Fiscal Year Report Period Start Report Period Ending Source
2015-16 July 7, 2015 Aug. 31, 2015 Report