Poplar River Bridge Load Capacity Upgrade

Event/Procurement ID: CT053004

This procurement closed on Wed, June 30, 2004 and was awarded to A.D. Williams Engineering Inc..

Description

The consultant shall provide the Department with the following: a list of three conceptual design options planned for the design phase, time schedules for design, design review, permitting, preliminary surveys, contract preparation and tendering, construction and contract supervision, and submission of the as-built drawings, in PDF or AutoCAD format and a cost estimate for completion of the Work.

Details

This procurement was a Request for Proposal, but does not seem to have been posted as an open competitive process. This tender data is included for information purposes only based on information gathered from GNWT Contracting reports.
Published:
Fiscal Year:
Buyer:
BIP Locations:
Fort Liard (Dehcho)
BIP Applies:
Yes
AIT Applies:
Yes

Process:
Request for Proposal
Method:
Open (Competitive)
Procurement Type:
Services
Category:
Engineering Consulting
Closing:
Status:
Awarded

Posted Bids (4 bids)

Bidder Status Bid Price NWT-Only Eligible NWT/Local Eligible Adjusted Bid Price Contract Price
A.D. Williams Engineering Inc. Successful -- -- -- -- --
Earth Tech (Canada) Inc. -- -- -- -- --
Jivko Engineering -- -- -- -- --
Ferguson Simek Clark -- -- -- -- --

Attachments

Filename Description Size Added
No files attached to this tender.
Note: You have to login to access attachments. For any questions about documents please contact the GNWT Contracts Portal.

Related Contracts

Fiscal Year Contract # Supplier BIP Status Supplier Location Original Value Change Orders Change Value Final Value
2004-05 CT053004 A.D. WILLIAMS ENGINEERING INC. BIP Registered Yellowknife $90,373.00 -- -- $90,373.00