Courthouse Roof Replacement

Contract ID: CT041515
Status

This contract was awarded by Public Works & Services to Rowe's Construction Ltd..

The contract is complete.

There were 0 change orders.

Dates
A rectangle of color grey representing the period of progress A circle of color green representing the start of progress A circle of color red representing the end of progress
Start Date
May 18, 2004
Current End Date
Aug 31, 2004
Potential End Date
Unknown

Description

Replace existing roof with SBS MBM roof assembly which includes new insulation, repair of vapour barrier, new curb build ups and a new roof access hatch.

Details

Fiscal Year:
Buyer:
Public Works & Services

Contract Dates:
to

Supplier:
Rowe's Construction Ltd.
Supplier BIP Status:
BIP Registered
Supplier Location:
Fort Simpson

Original Value:
$156,264.00
Change Orders:
--
Current Value:
$156,264.00

Community:
Hay River (South Slave)
Process:
Request for Tenders
Method:
Open (Competitive)
Procurement Type:
Construction
Category:
Building Construction General

Contract Added:
Jan. 24, 2018
Source:
Contracting Report

Contract Disclosure Report Entries

Fiscal Year Report Period Start Report Period Ending Source
2004-05 April 1, 2004 March 31, 2005 Report
2004-05 May 18, 2004 Aug. 31, 2004 Report