Stanton Hospital - HVAC Upgrades
Contract ID: CT100724
Status
This contract was awarded by Public Works & Services to Central Mechanical Systems Ltd..
The contract is complete.
There were 11 change orders.
Dates
- Start Date
- Oct 14, 2008
- Current End Date
- Apr 30, 2010
- Potential End Date
- Unknown
Description
Documents available through the PWS North Slave Office. Upgrading the existing HVAC.
Details
- Fiscal Year:
- Buyer:
- Public Works & Services
- Contract Dates:
- to
- Supplier:
- Central Mechanical Systems Ltd.
- Supplier BIP Status:
- BIP Registered
- Supplier Location:
- Yellowknife
- Original Value:
- $2,690,000.00
- Change Orders:
- $171,006.06 (11 changes)
- Current Value:
- $2,861,006.06
- Community:
- Yellowknife (North Slave)
- Process:
- Request for Tenders
- Method:
- Open (Competitive)
- Procurement Type:
- Construction
- Category:
- Building Construction General
- Contract Added:
- Jan. 24, 2018
- Source:
- Contracting Report
Change Orders (Contract Amendments)
Fiscal Year | Change Order Number | Change Order Value |
---|---|---|
2008-09 | 1. cc115641 | $12,381.60 |
2008-09 | 2. cc415204 | $9,660.00 |
2009-10 | 3. cc416178 | $30,035.14 |
2009-10 | 4. cc417232 | $20,073.50 |
2009-10 | 5. cc418492 | $13,398.00 |
2009-10 | 6. cc418923 | $3,694.30 |
2009-10 | 7. cc419035 | $35,060.37 |
2009-10 | 8. cc419710 | $76,541.85 |
2009-10 | 9. cc420484 | $39,267.30 |
2009-10 | 10. cc420574 | -$75,000.00 |
2009-10 | 11. cc424864 | $5,894.00 |
* The GNWT only publishes combined change order values so when there are multiple change orders in a fiscal year it is not possible to determine the reason or value for individual change orders.